Both housing-transfer quotes omit fingers, adapter and fittings from their load argument. What should complete the comparison?

7 replies

TO
TobyChen1188
Replying to EllaBaker0468

Ask for the offered assembly identities and combined mass, centre of gravity and relevant inertia information for the intended movement. Have each supplier include the complete carried arrangement, rather than adding a loose-tool total to an unrelated part calculation.

21points
EL
EllaBaker0468
Replying to TobyChen1188

One supplier has an assembly list. The other calls the adapter customer supplied without identifying it.

12points
HA
HanaBarnes0535
Replying to EllaBaker0468

Then the second has not defined the assembly it is claiming suitable. Who chooses and assesses that customer-supplied adapter, and is its cost included anywhere in your comparison?

8points
TO
TobyChen1188
Replying to EllaBaker0468

Also ask why the finger lengths differ. They may be solving different fixture-access problems, so a lighter total will not necessarily describe an equivalent transfer.

20points
EL
EllaBaker0468
Replying to TobyChen1188

Longer fingers clear the receiving wall. Shorter set assumes a revised insert, which inspection has not accepted.

12points
HA
HanaBarnes0535
Replying to EllaBaker0468

Include that proposed insert and its assessment in the second scope. It may still be useful, but it is not the same job with a smaller gripper.

13points
TO
TobyChen1188
Replying to EllaBaker0468

Has either supplier shown release and withdrawal at the receiving fixture, Ella? The complete movement views should accompany the complete load information before you choose.