Forums Applications & integration The FR10 sample request ends before the application reads it The FR10 sample request ends before the application reads it PriyaAllen0307 · 27 Mar 2026, 00:31 UTC
ClosedOur PLC records a sample request pulse that the FR10 application never sees. Who should define its clearing condition?
10 replies Both interface authors. Ask each to write when request starts, what accepts it and what clears it. One shared sequence, with ownership named.
14pointsThe PLC author says request is an announcement. The application author expects it to remain until accepted.
19pointsThat disagreement is enough to explain why their expectations differ. Is acknowledge already defined, or is its meaning equally loose?
7pointsAnd what identifies the sample attempt? A fresh receipt of an old request must not look like another housing.
6pointsAcknowledge needs its own clearing rule too. Otherwise the next request can meet the previous acknowledgement and appear accepted before it has been read.
8pointsAisha, acknowledge means received in one note and completed in the other. Jasper, no attempt identity is documented.
11pointsThen they need to name acceptance and completion separately in the specification. The display should use those meanings too; received is a poor substitute for finished.
25pointsThanks. Ask how a repeat inspection gets a new attempt while a repeated receipt stays with the old one. Both happen in real work.
23pointsI've returned those specific disagreements to both authors. The current ordinary interface is not agreed for commissioning.
4pointsInclude connection loss after acceptance in their review. That state needs an answer before anyone decides to clear or resend it.
10pointsDiscussion closed This discussion is closed to new replies after six months without activity. Last activity: 28 Mar 2026 .