FR10 stop report with the event time missing

LouisAli0224 · 29 Jul 2025, 22:24 UTC

Closed
LO
LouisAli0224
Our FR10 connector loader pauses intermittently. Seller has a video with no event time. What should accompany the next one?

11 replies

TO
TobyAli0231
Replying to LouisAli0224

Include the active step, exact message and fixture identity, linked to the same occurrence. An event reference is useful even if the phone and station clocks differ, provided you explain how the attachments belong together.

22 points
LO
LouisAli0224
Replying to TobyAli0231

New occurrence has the fixture ID, step and message. Phone time is offset from the station.

9 points
TO
TobyAli0231
Replying to LouisAli0224

Preserve both original times and record the measured offset for that capture. Don't rewrite one file's timestamp and hope nobody later needs to understand the difference.

8 points
LO
LouisAli0224
Replying to TobyAli0231

Done. The message names a fixture-ready wait. Sent the linked capture to support.

6 points
TO
TobyAli0231
Replying to LouisAli0224

What did support ask for after seeing that wait?

22 points
WI
WillChan1096
Replying to LouisAli0224

On one of our reports the fixture looked seated in the wide shot, but the relevant target was hidden. Can your maintenance person identify which physical condition supplies that ready input before taking more close-ups?

15 points
LO
LouisAli0224
Replying to WillChan1096

Support identified the input. Maintenance is checking its target and the fixture seating. No cause confirmed.

9 points
TO
TobyAli0231
Replying to LouisAli0224

That is a narrower question to investigate. Keep the original occurrence available so the maintenance finding can be compared with what the station reported then.

18 points
JA
JamieBrooks0817
Replying to LouisAli0224

Louis, did anyone actually find why the ready input was absent, or has the ticket just changed hands? Those are different kinds of progress.

12 points
LO
LouisAli0224
Replying to JamieBrooks0817

Target position differs on this fixture revision. Tooling is reviewing the intended arrangement before repair.

8 points
GR
GraceAllen0320
Replying to LouisAli0224

Identify that fixture revision in the stores record too, so a replacement target or fixture does not arrive under the old description while tooling reviews the change.

19 points

Discussion closed

This discussion is closed to new replies after six months without activity. Last activity: .