The good bracket dimension was written after straightening

IsaacBaker0520 · 9 May 2025, 06:02 UTC

Closed
IS
IsaacBaker0520
I followed a correction note on our old bracket sheet and found the accepted dimension was measured after a separate straightening operation. We're reviewing FR10 welding tooling, and the proposal treats that value as the fixture's output. I need the new handover to explain who handles the work if it remains.

6 replies

EM
EmmaBennett0724
Replying to IsaacBaker0520

Find any readings before straightening, for the same bracket variant. That accepted number cannot tell you what originally left the fixture.

4 points
IS
IsaacBaker0520
Replying to EmmaBennett0724

Only pass/fail marks before correction, no actual dimensions. The old operator remembers checking the gap near the top, but the sheet doesn't identify the measuring setup.

14 points
EM
EmmaBennett0724
Replying to IsaacBaker0520

Ask quality to define that setup for new measurements. Also check which drawing revision the old operator was working to before combining his recollection with the current part.

13 points
SO
SofiaBell0630
Replying to IsaacBaker0520

I'm dealing with a similar missing correction bench in another proposal. Has your layout made room for that work, or quietly assumed the new fixture eliminates it? That assumption can leave the operator with nowhere to finish the part.

16 points
IS
IsaacBaker0520
Replying to SofiaBell0630

It assumed the work disappears. We've held that part of the layout while quality and welding plan the trial. Thanks, I'll get the operator involved before the revised bench arrangement is drawn.

0 points
EM
EmmaBennett0724
Replying to EmmaBennett0724

Did you find the old drawing revision? That remains worth answering even if the new trial uses the current one.

16 points

Discussion closed