Bracket passed after correction, first released reading missing

GraceCarter1016 · 14 Feb 2026, 09:08 UTC

Closed
GR
GraceCarter1016
Our UR5e proposal inherits final passes. No first released readings. Cannot price how much correction those passes needed.

12 replies

LI
LiamBaker0490
Replying to GraceCarter1016

Can fabrication recover any linked correction records, or do you only have inspection's final results? Don't estimate the rate from whichever bad bracket somebody remembers.

24 points
GR
GraceCarter1016
Replying to LiamBaker0490

Only final inspection results linked by bracket. Fabrication's correction notebook lists a shift total, no bracket identities.

19 points
AN
AnnaArcher0416
Replying to GraceCarter1016

Our new traveller needed the first released measurement for exactly this reason. A final pass was doing too much work in the spreadsheet. Keep the incoming fit-up and fixture seating separate, then follow the same bracket through first release, any correction and the return check.

15 points
TO
TobyBell0666
Replying to GraceCarter1016

Can the old shift total still inform the labour budget as an unallocated total, provided nobody presents it as a per-bracket correction rate?

2 points
SO
SofiaBell0630
Replying to TobyBell0666

Toby, possibly, but Grace needs to know what else that shift total includes before using it. Waiting, several product types, or work done by a second person could change the interpretation.

23 points
GR
GraceCarter1016
Replying to SofiaBell0630

Notebook includes two bracket types and waiting for inspection. Useful workload note, not a correction time for this assembly.

15 points
LI
LiamBaker0490
Replying to GraceCarter1016

Then keep it beside the study plan, not inside a calculated correction rate. Who is choosing the current samples?

7 points
GR
GraceCarter1016
Replying to LiamBaker0490

Process specialist with quality. Both permitted fit-up extremes included. Current drawing and fixture set identified.

7 points
AN
AnnaArcher0416
Replying to GraceCarter1016

Who will write down the first released result before correction starts? That is the entry we kept losing between fabrication and inspection.

15 points
SO
SofiaBell0630
Replying to AnnaArcher0416

And make that practical for the person doing it. A form located at the final inspection desk won't capture an earlier stage by wishful thinking.

17 points
GR
GraceCarter1016
Replying to AnnaArcher0416

Inspector records first release at the agreed check station. Fabrication records correction; inspection records return result. Study not run yet.

0 points
TO
TobyBell0666
Replying to GraceCarter1016

That gives purchasing a defined study to cost, while the old mixed shift total stays visible without pretending it answers the assembly question.

6 points