What staff time belongs in my fixture-unloading pilot?

SofiaBell0630 · 18 Feb 2025, 06:01 UTC

Closed
SO
SofiaBell0630
I priced a UR5e and gripper for unloading connector housings, then showed the total to our production lead. She asked who makes the fixture, covers training and handles interruptions. Fair enough, my 'pilot cost' had a very selective memory. I'd like to propose one housing type and a limited supervised trial, with a budget that includes our own time. What would you make explicit before we agree it?

3 replies

MA
MayaChen1171
Replying to SofiaBell0630

Who will run the trial after you finish setting it up? Put that person's preparation and support time into the scope too.

22 points
SO
SofiaBell0630
Replying to MayaChen1171

Our assembly technician would run it, and hadn't been included in the estimate at all. We've now allowed time for her to review the workstation and trial a changeover. Fixture design is a separate quoted task. The lead is willing to review that version.

17 points
MA
MayaChen1171
Replying to SofiaBell0630

What result would make you stop? Agree that before the hours are spent, while everyone can still answer honestly.

17 points