Our UR5e bracket allowance still starts after the first released check

JoBell0679 · 18 Apr 2026, 01:40 UTC

Reply to discussion
JO
JoBell0679
Correction has a time allowance now. The UR5e proposal still skips the first released check that decides whether correction is needed. I want fit-up, locating, release and reinspection shown as actual stages, not free gaps.

1 reply

SA
SarahBrooks0850
Replying to JoBell0679

In our review the checking time vanished because the summary began at the correction bench; follow identified brackets through the full route, including those that pass directly, and keep active checking separate from waiting for inspection.