Connector unloading stop with no readable FR5 message

AlexBaker0472 · 10 Sept 2025, 15:27 UTC

Closed
AL
AlexBaker0472
Separate from my sleeve-loading ticket: our FR5 connector-unloading job also pauses, and its clip misses the message. Seller on Alibaba asks for more information. I want this report kept apart from the sleeve fixture, not diagnosed from its unfinished evidence.

5 replies

FI
FionaAllen0325
Replying to AlexBaker0472

Put connector unloading and the fixture identifier at the top. Then send one dated occurrence with the readable message, active step and matching logs. Make clear that the sleeve report is a different job, not a previous diagnosis of this one.

15 points
AL
AlexBaker0472
Replying to FionaAllen0325

Fixture C6. New capture says waiting for outgoing clearance, step 18. Matching records sent under the connector ticket. Still don't know which device supplies that clearance.

2 points
FI
FionaAllen0325
Replying to AlexBaker0472

Ask the controls contact to identify the expected condition and source for step 18 on that program revision. No point inspecting the sleeve fixture's detector just because someone already has its drawing open.

7 points
AL
AlexBaker0472
Replying to FionaAllen0325

Controls identified the receiving pocket's clear confirmation. Maintenance is arranging a capture of that state at the next occurrence. No cause established yet, but the two tickets now have their own attachments.

11 points
FI
FionaAllen0325
Replying to AlexBaker0472

Has the next shift got the receiving-pocket name and capture request too? The technical answer won't help much if the next clip is another close-up of the arm.

7 points

Discussion closed

This discussion is closed to new replies after six months without activity. Last activity: .