Our FR10 welding proposal copies old fixture geometry. Final checks followed straightening. What can those records actually support?

11 replies

YA
YasminBennett0702
Replying to CalebAllen0319

Find the readings before straightening, if any, and tie them to individual brackets. Otherwise you only know what the corrected parts measured, not what the fixture produced.

20 points
CA
CalebAllen0319
Replying to YasminBennett0702

No pre-correction sheet found. There is a clamped alignment check, with different reference faces.

1 points
JO
JoChan1114
Replying to CalebAllen0319

Then why is someone comparing those dimensions? We found different datums hiding under the same word 'checked'. Get the old instruction beside the final one before spending another meeting subtracting unrelated numbers.

25 points
DA
DavidAbbott0084
Replying to CalebAllen0319

On another bracket review we found the fixture copy belonged to an older gusset. Which part and fixture revisions do your sheets actually identify?

3 points
CA
CalebAllen0319
Replying to DavidAbbott0084

Bracket D on both. Fixture sheet says B; the proposed copy says A. I'm asking why.

25 points
AD
AdaAllen0303
Replying to CalebAllen0319

Could stores still have the B fixture drawing? I'd search that before asking someone to reverse-engineer the old photographs. Or rather, ask tooling who holds the controlled copy, not just the nearest folder

10 points
CA
CalebAllen0319
Replying to AdaAllen0303

Tooling found B. It includes a support absent from A. Purpose isn't described in the archived change note.

17 points
YA
YasminBennett0702
Replying to CalebAllen0319

Ask the old setter and welding lead about that support, with the drawing in front of them. I'd avoid transferring it as a requirement until its role is understood.

8 points
JO
JoChan1114
Replying to CalebAllen0319

And ask who did the straightening. The new cell doesn't get that labour for free just because it sits outside the fixture drawing. Does the proposed layout leave anywhere for it if it's still needed?

23 points
DA
DavidAbbott0084
Replying to CalebAllen0319

Caleb, keep the missing released measurement visible in the trial request. Discovering revision B is useful, but you still haven't found an untouched bracket result to compare.

20 points
CA
CalebAllen0319
Replying to JoChan1114

Layout assumed no straightening. That assumption is on hold; current-part trial still needs welding and quality agreement.

18 points